Home / Projects / Oberneisen rock ramp
River restoration · Water Framework Directive

A concrete weir becomes a rock ramp.

Restoring continuity on the river Aar: the fixed weir at Oberneisen was an insurmountable barrier for fish and invertebrates. WMEC redesigned it as a rough rock ramp – and saw the project through all nine HOAI service phases.

Client
Rhein-Lahn district authority, lower water authority
Watercourse
Aar, Oberneisen (Rhineland-Palatinate)
Scope
HOAI phases 1–9
Construction
Late June – early August 2005
Completed Oberneisen rock ramp seen from downstream: roughly paved ramp with boulder sills and grassed banks
46.61m³/s
Design discharge (50-year flood)
52m
Length of the ramp
1:40
Longitudinal gradient
8.50m
Width of the ramp
0.80m
governing head difference (1.30 m before)
52,857
construction cost, gross (final account)
Before / after

Same location, same view from downstream.

Before: a fixed concrete weir with a drop of 1.30 m. For fish migrating upstream it was a wall – only a few strong individuals made it past. The result: the population upstream declined and the aquatic community tipped out of balance.

After: a rough rock ramp with a 1:40 gradient, a parabolic channel and three bed-level boulder sills. The governing head difference falls to 0.80 m spread over 52 m – passable for all species, at low water and at flood.

Drag the slider to compare.

Before: the fixed concrete weir at Oberneisen with its drop, seen from downstreamAfter: the completed rock ramp with boulder sills and grassed banksBefore · concrete weirAfter · rock ramp
View from downstream · before constructionView from downstream · at completion
Technical solution

The figures behind the ramp.

A rock ramp has to do two things at once: provide enough depth and low flow velocity for fish at low water – and stay stable at the design discharge of 46.61 m³/s. The parabolic channel, raised by 22 cm, concentrates the flow in the middle when there is little water; the three boulder sills stabilise the bed and create resting zones.

The basis was our own river survey and the hydraulic calculation of the water surface profiles – both from one office, with no loss at the interface.

Technical data · as built
Design discharge (50-year flood)46.61 m³/s
Length52 m
Longitudinal gradient1 : 40
Ramp width8.50 m
Bank slope1 : 1.5
Channelparabolic, raised by 22 cm
Head difference before1.30 m
Governing head difference0.80 m
Special feature3 boulder sills at bed level
Construction timeJune – August 2005
Cost (final account)€52,857.33 gross
HOAI service phases
1
Basics
2
Preliminary
3
Design
4
Permitting
5
Detailed design
6
Tender preparation
7
Tender support
8
Site supervision
9
Aftercare
+1,30+0,80+0,30±0,000 m26 m52 mBEFORE · concrete weir · 1.30 m dropAFTER · rock ramp · 1:40 over 52 m3 boulder sills, at bed levelΔh 0.80 m
Schematic longitudinal section, not to scale. Values from the WMEC construction design.
Construction design

Site plan 1 : 500 – drawn by WMEC.

Weir, planned ramp, site road, DN 600 gas main and parcel boundaries in a single drawing. The basis for tendering, the authority and the contractor.

← SWIPE TO ENLARGE →
Construction site plan of the Oberneisen rock ramp with the river, the weir, the planned ramp, the site road, the DN 600 gas main and land parcels
Site road / gravel trackDN 600 gas mainRiver AarWeir (existing)Planned rampConstruction design · site plan · 1:500
Project sequence

From survey to handover – from one office.

For the client that means one point of contact, one contract and no friction between surveying, hydraulics, design and site supervision. Six weeks of construction – in summer, at low water.

  • PHASES 1–2River survey & basics

    Recording the weir, bed, banks and cross sections above and below. Determining the design discharge.

  • PHASE 3Hydraulic calculation & design

    Water surface profiles for low, mean and flood flow. Setting the 1:40 gradient, ramp width and boulder sills.

  • PHASE 4Permitting

    Application documents for the lower water authority – here also the client.

  • PHASES 5–7Detailed design & tendering

    Site plan 1:500, detail drawings, bill of quantities, tendering and award of the construction works.

  • JUNE – AUGUST 2005Site supervision (phase 8)

    Removal of the concrete weir, construction of the ramp in the low-water window, setting out and control surveys by WMEC.

  • PHASE 9Handover & documentation

    Final account €52,857.33 gross. As-built documentation for the client.